AT THE HEART OF THE ROAD TRANSPORT INDUSTRY.

Call our Sales Team on 0208 912 2120

TUNNELLING BEGINS • Work is to start next month on

4th October 1986, Page 31
4th October 1986
Page 31
Page 31, 4th October 1986 — TUNNELLING BEGINS • Work is to start next month on
Close
Noticed an error?
If you've noticed an error in this article please click here to report it so we can fix it.

Which of the following most accurately describes the problem?

a £165 million tunnel that will carry the A55 Chester-Bangor road under the River Conway Estuary near Llandudno, North Wales.

The 1.1km tunnel should be completed by January 1991. It is the largest single trunk road scheme ever awarded in the UK and it goes to a joint venture company set up by contractors Costain and Tarmac.

The A55 coast road carries traffic between Holyhead and the North West of England. In addition to the tunnel, the scheme will involve building 13 bridges, including a viaduct.

Tags

Locations: Chester

comments powered by Disqus