ROADWORKS THESE are sonic of the major road works that
Page 29
If you've noticed an error in this article please click here to report it so we can fix it.
may be encountered during the next week. We have not repeated the longer-running roadworks mentioned in previous weeks although they may soli be causing delays.
• M4 Severn Bridge. Over this weekend .(Februarv 28March 2) die left-hand lane of eastbound carriageway will be closed.
• M5 Midlands. Between.
junctions 2 and 3 (Oldbury and 1 lalesowen) the northbound carriageway is closed for 4.1km for carriageway strengthening.
• M5 Cheshire. Between junctions 17 and 16 (Sandbach and Stoke) there will be lane closures in both the north and southbound carriageways tbr 4k iii. These start this weekend (March 1) and will run until. March 23.
• M11 Essex, At junction 5 (Loughton/( higwell) there are lane closures on both carriageways.
• M20 Kent. At junction (Bearsted) only the righthand lane ul the westbound carriageway is open. Tins is due to patching works which are scheduled to last until March 8.
• M56 Cheshire. Between junctions 14 and 16 (1lelsby md Bickford) there will be a total closure of the motorway thus weekend (March I and 2) for 8kin. Traffic will be diverted on to the A5117.
• A2 Kent. Carriageway improvements are taking place at Luton Arches, Chatham. Traffic is being diverted.
• A4 London, The Great West Road near Transport A venue, Brentford, is being widened. I h L! eastbound carriageway is reduced to single-line traffic.
• A20 Kent. In Ashford there is excavation ,ind reconstruction of the dual carriageway, meaning contrallow working on the eastbound carriageway until late April,