AT THE HEART OF THE ROAD TRANSPORT INDUSTRY.

Call our Sales Team on 0208 912 2120

Bridgnorth

16th October 1982
Page 9
Page 9, 16th October 1982 — Bridgnorth
Close
Noticed an error?
If you've noticed an error in this article please click here to report it so we can fix it.

Which of the following most accurately describes the problem?

THE LONG-awaited by-pass at Bridgnorth, Shropshire, gets under way this month following the acceptance by the County Council of a tender of E2.25m for the construction of a new bridge over the River Severn.

The contract started on October 11 with a two year construction period.

The bridge, forms part of a £5m scheme to ease a major bottleneck through the historic town.

A £140,000 tender has also been accepted for a new bridge under the Severn Valley Light Railway, to take the Bridgnorth by-pass through a railway embankment.