AT THE HEART OF THE ROAD TRANSPORT INDUSTRY.

Call our Sales Team on 0208 912 2120

Main frame members

13th May 1966, Page 74
13th May 1966
Page 74
Page 74, 13th May 1966 — Main frame members
Close
Noticed an error?
If you've noticed an error in this article please click here to report it so we can fix it.

Which of the following most accurately describes the problem?

MACHINE-welded, lightweight, I-section main frame members made in high-tensile steel for use in semi-trailer construction are being offered by an associate company of the Primrose group.

The frames are machine welded to a high standard on an automatic welding machine built by the company, P. D. S. Fabrications Ltd., with the help of British Oxygen Co. Ltd. at a cost of £5,000.

Three basic frame depths are offered as standard. These are I-section beams with the following dimensions. The first has a 16in.-deep by 0.25in. web with 4in. by 0.375in. flanges with the main depth of the beam reduced to 8in. at one end. The second beam has similar dimensions, but employs 0.5in.-thick flanges and has the neck section reduced to 9in. The third beam employs a 20in.-deep web reduced to 9in. in the neck and to I6in. in the area where the running gear would be attached. This also employs 0.5in. flanges.

Beams are constructed from two qualities of steel. The webs are made from material having a tensile strength of 28-29 tons and the flairges from high-tensile 34/35-ton material. An added advantage claimed for the members is that being fabricated from flat plate they provide simpler fixing points to attach the various pieces of equipment that the modern trailer carries.

Initial production figures stand at 10 pairs of frames per week, but later it is hoped to increase this to around 50 pairs per week. Made by: P. D. S. Fabrications Ltd., Woone Lane, Clitheroe, Lancs. Price: Per pair of 281t. long, 16in. by 4in. bY 0.5in., £65. Extra length: £2 3s. per ft. per pair.