AT THE HEART OF THE ROAD TRANSPORT INDUSTRY.

Call our Sales Team on 0208 912 2120

Chunnel ready for freight

13th February 1992
Page 7
Page 7, 13th February 1992 — Chunnel ready for freight
Close
Noticed an error?
If you've noticed an error in this article please click here to report it so we can fix it.

Which of the following most accurately describes the problem?

• The Channel Tunnel will be three months late in opening, but hauliers can expect a full freight service from day one, according to Eurotunnel.

The freight shuttle trains and through trains are due to operate at full capacity from the end of next summer: there has been talk of delays in the provision of a full freight shuttle service.

The three-month delay caused by a slow down in its construction will also allow Eurotunnel to convert more of its semi-open freight shuttles to a closed design — the open design has been slammed by safety experts as a fire risk.

Tags